Board hears updates on buses, HVAC and roofing projects; three new buses have arrived

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Operations staff told the board that three of five new buses have been delivered, HVAC and roofing projects are underway at multiple schools, and unexpected repairs and summer scheduling are being managed to avoid disrupting events.

Operations staff updated the board on transportation and facilities work, including new buses, roofing, HVAC and field/milling schedules.

Transportation: Staff reported three of five new school buses have arrived and the remaining two were expected later in May; the district intends to issue a new letter of intent to start the next purchasing cycle. Parents at affected schools will get information about route changes when finalized.

Facilities: Roofing repairs at Windsor High and Smithfield Middle are underway; production slowed briefly for SOL testing but continued on weekends. Smithfield High’s paving schedule was adjusted to avoid senior nights and other events; crews were scheduled to mill and pave on May 19 subject to weather and activities.

HVAC: Carrollton Elementary HVAC replacement work is starting May 19 in non‑instructional areas. Staff explained the accepted low bid for the Carrollton HVAC contract came in at about $5.7 million, below a planning estimate of $7.4 million; officials cautioned that additional costs (temporary storage, furniture moves, relocation logistics) still add to project totals.

Other repairs: Staff listed several unanticipated repairs completed or in progress, including drainage and smoke‑detector work at the land lab, repaired field lights and tennis court drainage pipe issues, replacement of the Windsor High weight room HVAC, and concession‑stand fixes needed to pass health inspections. Staff said some smaller projects didn’t meet capital request deadlines and are being handled as operating repairs.

Board members thanked staff for coordinating around school events and for prioritizing safety. No formal action was required beyond continuing project oversight and scheduling.