Crowley officials say years of drainage neglect fueling recurring neighborhood flooding; crews prioritizing emergency spots
Summary
Street commissioner and public works staff described months of emergency and routine work addressing blocked ditches, collapsed catch basins and a collapsed culvert; councilors pressed for faster repairs and more staffing.
Get email alerts on the Drainage And Public Works topic
No spam. Unsubscribe anytime.
Crowley street officials said the city is tackling years of deferred drainage maintenance after heavy spring rains left multiple neighborhoods repeatedly flooded. Street Commissioner Wesley Jacob told the council that crews have reshaped about 3,000–4,000 linear feet of ditches, cleared roughly 2,000 feet of cover, and are working catch basins and collapsed pipes across town.
“Grass has been in full effect since January,” said Street Commissioner Wesley Jacob, describing the season’s demands. “We’ve been asking for help from the community because we just can’t take it all…we're trying our best.”
The council heard specifics on problem sites: a collapsed under-road drain on Seventh Street at Ross that requires work after school ends; a blocked pipe heading east on Cedar Street that crews could not yet trace with a camera; persistent drainage problems near South Avenue J and Huff Power that forced overnight work to chip concrete and clear collapsed basins. Public works director Albert John reported vehicle and equipment maintenance needs at the department, including a dually with a suspected head leak and bushings needed on a wastewater “guzzler.”
Mayor and council members pressed Jacob and staff for clearer schedules and faster response to individual complaints after residents said they had not received callbacks. Jacob said crews prioritize active flooding, then work back through less-urgent requests: “If I see something flooded, that's my priority.” Mayor and other councilors pushed for lists and work orders so residents would know where an item stands.
Councilors repeatedly cited limited staff and equipment as constraints. An alderman suggested hiring more workers; Jacob said the shortage and budget limits mean the street department must triage emergency calls and gradually address long-neglected ditches and culverts. Jacob and the mayor said they have coordinated on specific problem locations and will present options when further facts and cost estimates are available.
The council also discussed mosquito-control plans tied to wetter weather. Public works said spot spraying will continue as needed before the regular weekly spray cycles begin the first week of June; staff will inspect problem sites when residents call.
Nut graf: The discussion framed recurring neighborhood flooding not as a single failure but as the cumulative effect of years of postponed maintenance; city staff described targeted actions and emergency responses, while council members and residents demanded clearer timelines and more staff to move from reactive fixes to sustained repair work.
Background: Council members said much of the city's drainage system — clay pipes, older catch basins and long-untouched ditches — dates back many years and is beginning to fail in multiple locations. Jacob said the city is “fixing the problems as we get to them” and that some repairs will require cooperation from parish drainage boards and, in at least one case, infrastructure replacement once parts and contractor schedules align.
What’s next: City staff will advance a project plan for the Seventh Street at Ross repair after school lets out, continue TV-camera work to locate the Cedar Street blockage, and keep a prioritized work-order list so residents know when their requests will be handled.