Facilities director reports seismic upgrade timeline, water testing and recent donor‑funded improvements
Summary
Facilities staff reported on a seismic rehabilitation at Silvercrest (beginning June 2), ongoing mandated water testing (including PFAS baseline testing later this year), a new paved and lighted lot completed with donors and Fox Foundation help, and other small capital tasks; completion of the seismic work is planned before the next school year
Get email alerts on the Facilities Maintenance topic
No spam. Unsubscribe anytime.
Jeff (facilities director) gave the board a facilities update covering several active projects and state testing requirements.
He reported that a seismic rehabilitation project at Silvercrest is scheduled to begin June 2 with storage containers and on‑site staging already in place; the contractor found missing footings during preliminary exploration and added foundations, and the project remains on schedule for substantial completion in August so the building can be ready for the next school year.
Jeff also described ongoing water testing required by the state for seven district well systems, including VOCs/SOCs this season and a planned PFAS baseline test later in the year (state‑shipped tests expected in August). He said the arsenic mitigation system at one site (BP/Blanton?) is working and is monitored monthly.
Jeff thanked community donors and the Fox Foundation for a quick, volunteer‑led upgrade of an old gravel lot, adding pavement, striping and lighting; he said the lighting has improved perceived safety and the surface reconfiguration was a "game changer" for student activities. He noted other maintenance work in planning: a kitchen hood repair at Robert Frost, parking lot striping at outlying schools, and relocation of the pre‑K program to Robert Frost.
Ending: Facilities staff said they will return with test results and further scheduling details; Silvercrest seismic work is on track for completion before classes resume in fall.