Derby IT warns of $298,015 shortfall in E‑rate network refresh; staff to seek district funding
Summary
Assistant director of technology said Universal Service Administration (USAC) reduced Derby’s E‑rate support for a planned network refresh, increasing the district’s share by $298,015.62; staff said the amount was already budgeted in the five‑year capital plan and will be brought back for approval.
Get email alerts on the Education Technology Funding topic
No spam. Unsubscribe anytime.
Derby Public Schools’ technology staff told the board May 12 that federal E‑rate support will not cover the full cost of a planned network refresh, leaving a $298,015.62 shortfall the district must cover.
Joshua Vanoy, assistant director of technology, said the Universal Service Administrative Company (USAC) notified the district on May 1 that the budget allocated through E‑rate was insufficient to cover the full 60% discount the district expected for the network refresh project. Vanoy said the district had previously approved $772,249.68 as the district’s portion and that the newly identified shortfall is $298,015.62.
Vanoy told the board the district had budgeted for the full amount within the five‑year capital outlay plan and that staff will return at the next meeting with a formal request to approve the additional $298,015.62 to fully fund the district’s share of the project.
No formal board action on the additional funding request was taken at the May 12 meeting; Vanoy presented the adjustment for discussion and planned a request for approval at the next board meeting.