Public Works update: 40th Street repairs, sanitary sewer lining and citywide projects advance
Summary
Fargo Public Works presented monthly construction updates including the 40 Fifth Street concrete repair phases, sanitary sewer lining and upcoming concrete and shared‑use path work; one minor on‑site injury was reported.
Get email alerts on the Infrastructure.streets Sewers topic
No spam. Unsubscribe anytime.
Fargo Public Works delivered its monthly construction update to the City Commission, detailing active rehabilitation and new‑development projects across the city and noting one on‑site safety incident.
The nut graf: Work on major corridors and utility systems continues this season while the city invests in mapping and resident information tools to make project details more accessible to the public.
Tom Nokoskin and Public Works staff flagged a safety incident: an employee on the 40 Fifth Street project injured a hand operating a tool and required medical attention but has since returned to work. Staff highlighted a new public portal, fargostreets.com, which includes interactive project maps and pages for residents to find current project details.
Highlighted projects include the 40 Fifth Street concrete pavement repair between the interstate and 30th Avenue, currently in phase 1 with subsequent phases planned later in the year; a sanitary sewer lining project focused on mainline and laterals intended to reduce the need for full sewer replacements; and multiple shared‑use path builds such as the River Drive work east of University. Staff showed images of potholing and directional drill operations used to locate utilities and install liners.
New development projects were also listed, including work north of the Amazon Dakota Commerce Center and the Interstate Business District, and a storm lift station (Lift Station 27) with 78‑inch and 60‑inch pipes under construction. Staff reported a major earthwork project in the Southwest Metro area involving about 1.5 million cubic yards of excavation.
Public Works also said an upcoming city concrete spot repair at Broadway and Second Avenue (Area 8) will begin a week from the report and will last about nine days; pedestrian detours and temporary ramps will be provided. Staff said a number of core neighborhood reconstruction projects, crack fill, mill and overlays, sidewalk replacements and storm sewer repairs are scheduled this season.
Ending: Staff invited commissioners to follow project maps on fargostreets.com for updates and to contact public‑works staff with questions; no commission action was requested.