Council hears animal shelter progress: $861,000 raised, about $450,000 short to finish interior
Summary
City staff and volunteers reported construction progress at the new Rolla Area Animal Shelter, fundraising results and a remaining funding gap. The council was asked to allow a $25,000 procurement limit for the project using donation funds; council agreed to consider a resolution at the next meeting.
Get email alerts on the Community Facilities Animal Shelter topic
No spam. Unsubscribe anytime.
City staff and the shelter fundraising committee gave the council a detailed update on construction and fundraising for the new Rolla Area Animal Shelter.
Background and construction status: Staff said the project began with a 2014 feasibility study that estimated a roughly $1.9 million facility. The city launched a capital campaign after receiving $441,000 from the late Bob Eck’s estate and later authorized construction of a shell so the donation would be used for bricks-and-mortar rather than erode with inflation. Contractors have completed the shell, under-slab plumbing in the kennel area, interior framing and much of the interior electrical; staff said the building includes 26 primary kennels that can be doubled by opening guillotine doors to outside runs.
Finances and fundraising: Campaign leaders reported total donations received of about $861,000 and total expenditures (through January) of about $721,000; staff said the current spending to date is closer to $750,000. The total project target remains about $1.5 million (city target) to $1.9 million (initial 2014 estimate) and the committee estimates a remaining shortfall of roughly $400,000–$450,000 to complete kennels, HVAC, site work, furnishings and equipment.
Fundraising activities noted in the packet include the Rainy Run, memorial gifts, the Day family adoption room gift, corporate gifts and smaller community events. The committee described a major fundraising event scheduled for April 26 at the Diamond Event Center; committee volunteers hope the event could raise $40,000–$50,000 and target specific elements such as FF&E or HVAC.
Procurement request: Staff requested council flexibility to allow use of fundraising dollars to authorize purchases up to $25,000 without returning to council for every vendor contract (staff said the current authorized city procurement expenditure limit is $10,000). Staff proposed bringing a resolution at the next council meeting to create a temporary, project‑specific procurement threshold for the shelter building fund; several council members said they supported bringing that resolution for formal action at the next meeting.
Next steps and timeline: Staff said they are pursuing incremental completion using volunteers, city crews and limited contracting to open sooner rather than waiting for a single turnkey fundraising goal. Council instructed staff to return with the requested resolution and the project team said they would continue fundraising and report back on event outcomes and future expenditures.