Committee approves repair work on two Rock Hollow bridges after inspection flagged undercutting

3717053 · March 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The committee authorized immediate repairs to two bridges on the Rock Hollow section of the Cabo Trail after inspections found undercutting and creek back-up; T Hill Construction provided an estimate of just over $25,000 covered by the park maintenance budget, and the work was approved by voice vote.

Director Vinich reported that bridge inspections at Rock Hollow identified structural concerns related to scour and undercutting at two small pedestrian bridges. Great Rivers Greenway performs periodic inspections for the valley, and two bridges returned concerning results this year.

T Hill Construction — a contractor under the city’s annual maintenance contract — provided an estimate of just over $25,000 to repair the two structures. Vinich told the committee the funds are available in the park maintenance line.

Council Member Ramberg moved to proceed. “This is, clearly a safety issue. We have to do this,” Ramberg said on the floor. Committee members discussed repair methods: one member warned against a short-term “riprap only” approach and asked staff to confirm materials and methods; staff said they will incorporate boulders the contractor can source from a nearby project and would seek a durable solution aimed at preventing repeated erosion.

Action: Committee approved the repairs as outlined and authorized staff to proceed with T Hill Construction under the existing maintenance contract so the work can be completed and re-inspected.