Ozark staff seek change order for Findlay River lift station project to realize efficiencies
Summary
Public Works Director Jeremy Parson asked aldermen to approve change order No. 1 to a Smith & Edwards Construction contract to complete the Findlay River lift station and 22,000 linear feet of force main, citing ARPA funding and cost savings from contractor continuity; board held the bill over for a future meeting.
The Board of Aldermen heard a detailed update and a request to authorize change order number 1 to the Smith and Edwards Construction Inc. contract for the Findlay River lift station and force main improvements (bill 3637).
Jeremy Parson, the city's public works director, said the project installs roughly 22,000 linear feet of force main and constructs a new Findlay River lift station intended to eliminate two siphons and a force main under the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat