Council awards Spring Street resurfacing contract after bids come in under budget

3686418 · April 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a bid award to E.R. Snell for Spring Street resurfacing April 14 after staff described the city’s pavement condition index work and available funding; the low bid came under staff’s estimate and leaves about $1 million unspent in the current resurfacing allocation.

The Tucker City Council approved a construction contract April 14 to resurface a cluster of streets that staff assembled from the city’s pavement management study, awarding the work to E.R. Snell for $2,859,000 plus a 5% contingency.

Why it matters: the city uses a periodic pavement condition index (PCI) study to prioritize resurfacing. Maintaining an upward PCI trend was a stated council objective; staff recommended a multi‑year funding target of roughly $4.5–5.0 million to preserve pavement conditions.

What staff told council: staff summarized past PCI studies and mapped resurfacing work completed since 2018. Staff said last year’s inventory and analysis guided the current list and that the city had about $4.6 million available in FY25 from SPLOST, state funds and capital allocations. Bids were returned lower than some estimates; E.R. Snell’s low bid was characterized as an outlier but a reputable, experienced contractor. Staff noted the largest item on the proposed list was Henderson Road (funded through a state grant set aside). The award includes a 5% contingency and is funded by a mix of state funds, SPLOST and the FY25 resurfacing allocation.

Council discussion: councilmembers noted the visible progress in road conditions and encouraged staff to use the remaining funds quickly or roll them into next year’s resurfacing program; staff said rules require re‑bidding additional scope but agreed to pursue a follow‑on contract or include the unspent amount in next year’s plan.

Vote and next steps: council voted unanimously to award the contract and move forward; staff will schedule construction and return with updates on additional streets to add if unit pricing and timing permit.

Ending: staff reminded residents that the city’s public works website can be used to report potholes and immediate concerns between resurfacing cycles.