Oneonta staff outlines sidewalk repair plan, $40,000 budget and use of Job Corps for labor
Summary
Public works staff said $40,000 is budgeted for sidewalk repairs this year, with material costs covered and Job Corps providing labor for many repairs; staff discussed prioritizing River Street ADA tiles and exploring sidewalk condition scanning for 2026 budgeting.
Get email alerts on the Sidewalks Infrastructure topic
No spam. Unsubscribe anytime.
Committee members questioned the city’s sidewalk budget and repair priorities; public works staff described current funding and planned work.
Chris (public works) said the city has $40,000 budgeted this year for sidewalk repairs and that a significant portion of that funding will pay for materials while Job Corps will supply much of the labor for July and August. Staff said materials include concrete, wire mesh and curing agents and that CHIP (Community Housing Improvement Program) funds will cover ADA tile work on River Street (from Parrish Avenue to the end).
Staff said Job Corps will not perform all work because some arterial sidewalks and high‑traffic areas are beyond Job Corps’ scope and will require conventional contracting; those contracts carry higher costs. The city discussed doing a formal sidewalk condition scan (similar to a recent street‑scan) to prioritize repairs as part of 2026 budgeting. Committee members discussed ownership: staff said sidewalks are within the city right‑of‑way and the city has historically maintained and replaced sidewalks, although other municipalities sometimes place responsibility on property owners.
Ending: Staff will continue planned River Street ADA work funded by CHIP and will consider a sidewalk scan and budgeting options for 2026; Job Corps labor is scheduled for summer months and materials will be funded from the $40,000 sidewalk budget.