Council approves change orders totaling net negative adjustments for Oswego Riverwalk west wall project

3683399 · May 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Oswego Common Council on May 12 approved multiple change orders for the Riverwalk West Wall Reconstruction Project, including additions and a negative closeout adjustment that together reduced earlier billed quantities.

The Oswego Common Council voted May 12 to approve a series of change orders for the Oswego Riverwalk West Wall Reconstruction Project that include both additional payments and a negative closeout adjustment.

By roll call the council authorized change order number 6 with JMT Incorporated in the amount of $68,918.85 for wall repairs, change order number 7 in the amount of $8,660.33 for scaffolding and fall-protection removal, and change order number 8 in the amount of $52,581.26 for overruns and owed payments from 2024. The council then approved change order number 9 in the amount of negative $91,477.58 to close out and remove unused items and quantities from the project.

All four change orders were approved by recorded roll call votes listed in the minutes; the resolutions each passed with a 6-0-1 tally (six yes, zero no, one absent).

A councilor who spoke during the item emphasized the Riverwalk’s recreational and economic value, calling the waterfront “our most valuable asset” and saying the completed project should help revive tourism and fishing activity. The councilor said completing the Riverwalk was especially meaningful in the speaker’s final year on the council.

The change orders were presented sequentially on the agenda, and no formal amendments to the amounts recorded in the minutes were noted during the meeting. The council’s approvals move the reconstruction project toward closeout while accounting for both added costs and deductions for unused items.