Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Montgomery County EDA hears update on Falling Branch Lot 2; stormwater permit and pump station ownership undecided

3676915 · March 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

EDA staff reported progress on grading and utilities at Falling Branch corporate park Lot 2, described permit and weather delays, noted a $347,265 contractor work estimate for payment application No. 8, and summarized an earlier EDA-approved pump station study sized at 25,000 gallons per day.

The Montgomery County Economic Development Authority on a construction update reported that work on Falling Branch corporate park Phase 2, Lot 2 has advanced but remains delayed by winter weather and a pending stormwater permit revision.

EDA staff said Main Street Builders finished the water line in late February and that the contractor’s recent work for payment application No. 8 totaled about $347,265. Staff said permit processing and repeated weather days have pushed the schedule: a 45-day permit review plus 78 weather days were counted in the project’s timeline. Staff previously estimated a “substantial completion” date in mid-May but also noted an objective to complete initial reviews by March 26 for certain work elements.

The update said…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans