Summary

The Choctaw County Commission approved a $26,400 invoice for construction management and discussed a temporary closure and repairs on Zalupa Road, plus paving work at McCarty's Ferry and staffing for engineering tasks.

The Choctaw County Commission on an unnamed date approved payment to Grama Management LLC and discussed a temporary closure and related repairs on Zalupa Road (County Road 8), emergency access plans and a paving schedule for McCarty's Ferry.

Commissioners voted to approve a $26,400 invoice from Grama Management LLC related to the county's previously approved minimum cut-off project and authorized the probate judge and county administrator to sign the invoice. "This is just a partial payment to pay for what she's done up to this point," the county engineer said when recommending approval.

The engineer reported inspecting the Zalupa Road site and said more drainage work remains. He requested a temporary road closure for drainage repairs on Zalupa Road, described as about a half-mile west of Howard 17, "approximately from 8AM to 12AM." He said he would try to get a single lane open as quickly as possible and asked staff to notify families who live on the road so residents could plan ahead.

Commissioners and staff discussed emergency access if the road is closed. The engineer said he would have dump trucks and loaders ready to fill the hole quickly if needed and that the county could open the road for emergency vehicles within minutes. He gave technical details about the repair: the pipe segment is about 50 feet long and work would replace or partially replace pipe sections; he also discussed using a 48-inch pipe where feasible.

The engineer said crews started prep work on McCarty's Ferry and planned to put in centerline striping and begin paving, aiming to complete the project in about three weeks, barring other emergencies that would require redirecting staff. He said paving would use most county road employees while the work is underway.

On procurement and contractor relationships, the engineer said Hosey Weaver had been acquired by APAC and that APAC is honoring annual contracts; he discussed hauling and the county's preference to provide in-kind hauling to meet its contribution share where possible.

The commission's discussion also touched on staffing and capacity: the engineer reported only one external application for an assistant engineer position and said the county currently contracts out some bridge inspections because of limited in-house time; he asked the commission whether to recruit actively.

Ending: The commission approved the Grama Management LLC invoice and directed staff to notify affected residents about the Zalupa Road closure, pursue the needed drainage repairs and proceed with McCarty's Ferry paving as scheduled.