Fayetteview Parkway 18% complete; regional lift station ready, TxDOT widening planned in three years
Summary
Public works staff reported progress on Fayetteview Parkway (about 18% complete), completion and testing of a regional sewer pumping station ready for service, and notification from TxDOT that widening of Highway 5 is planned for letting in three years.
Town engineering staff updated the council Feb. 4 on several construction projects, reporting progress on the Fayetteview Parkway project, completion of a regional sewer pumping station, and early coordination with TxDOT on a future Highway 5 widening.
Engineering staff said Fayetteview Parkway is about 18% complete after approximately three months of work; crews have installed storm sewer sections and begun…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat