Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Chesapeake Bay Exceptions And Wetlands Permits topic
No spam. Unsubscribe anytime.
James City County boards approve shoreline nourishment, six Chesapeake Bay exception requests with conditions
Summary
On April 9, 2025, the James City County Wetlands Board and Chesapeake Bay Preservation Area Board approved a wetlands permit for beach nourishment at Cypress Isle and granted six CBPA exception requests, including an after-the-fact accessory structure on Osprey Drive subject to a modified mitigation and completion timeline.
Get email alerts on the Chesapeake Bay Exceptions And Wetlands Permits topic
No spam. Unsubscribe anytime.
James City County’s Wetlands Board and Chesapeake Bay Preservation Area Board met April 9 and approved a wetlands permit to replenish beach sand at 1812 Cypress Isle and six Chesapeake Bay exception requests, most with conditions requiring mitigation, sureties or time-bound compliance.
Staff said the wetlands permit, WJPA 25-0008, would replenish previously authorized beach fill and plant 663 Spartina plugs, and recommended approval with a $3,500 surety and a permit expiration of April 9, 2028. Emily Grojean, watershed planner, told the Wetlands Board that the original permit (VMRC permit No. 09-1044) had authorized revetments and 13,680 square feet of beach nourishment and that recent wave action had eroded the fill. “To stabilize the current shoreline,” Grojean said, the applicant seeks replenishment.
The Chesapeake Bay board then considered six exception requests at properties across James City County. Staff recommended approval of most applications as either minor or administrative impacts, with specific mitigation and surety amounts. The board voted unanimously on each case; several approvals included conditions that require the applicants to obtain all federal, state and local permits, submit mitigation plans, post surety, and record affidavits at the Williamsburg–James City County courthouse.
Votes at a glance
- Wetlands Board case WJPA-25-0008 (1812 Cypress Isle): Motion to grant wetlands permit for beach replenishment and 1,800 square feet of planting with 663 Spartina plugs; staff recommended a $3,500 surety; permit to expire 04/09/2028. Motion passed 5–0.
- CBPA-25-0022 (240 Jefferson’s Hundred — Lynch): After-the-fact exception for a house addition and to bring existing gravel landscaping into compliance; impacts 1,860 sq ft of new impervious in the RPA; mitigation required 4.5 planting units (50 shrubs) and $3,500 surety. Staff described impacts as moderate and recommended approval with conditions. Motion passed 5–0.
- CBPA-25-0021 (7260 Osprey Drive — Cameron): After-the-fact exception for an accessory building and driveway extension with approximately 4,000 sq ft of RPA impacts. Staff recommended denial and removal of the structure, citing major impacts and unmet prior conditions, and requested double mitigation (20 planting units) and a $15,000 surety if the board approved. The board instead approved the exception with amended conditions: the applicants must bring the structure into compliance with the floodplain ordinance, submit a mitigation plan and surety adjusted to reflect the agreed reduction in mitigation after the applicant agreed to remove a roughly 250-square-foot shed, and meet a July 9, 2025 completion date for plantings, garage modification and required surveys/elevation certificates. The motion as amended passed 5–0.
- CBPA-25-0020 (104 Poway Circle — Kennedy): Exception for retaining walls and removal of an unapproved dock and stone landscaping; total RPA impacts 252 sq ft; mitigation 1 planting unit with $1,000 surety; staff recommended approval. Motion passed 5–0.
- CBPA-25-0025 (5 Tay River — Lockwood): Exception for a walkway, patio and fire pit; impacts 395 sq ft in the seaward 50-foot RPA; mitigation provided exceeded requirements (2 understory trees and 12 shrubs) and staff recommended approval with a $1,000 surety. Motion passed 5–0.
- CBPA-24-0069 (108 Colonel Philip Johnson — Phillips/Marquee Homes): Exception for a new single-family dwelling on a lot where 95% lies in the RPA; total RPA impacts 4,075 sq ft and required mitigation of 10 planting units; applicants proposed 11 planting units plus two rock-garden BMPs. Staff described impacts as major but recommended approval with conditions including a $5,500 surety, HOA approval for the building setback crossing, and written installation verification. The board voted 5–0 to approve the exception with staff conditions.
Board deliberations and key details
The most contested matter was the Osprey Drive after-the-fact case (CBPA-25-0021). Staff had documented prior interactions dating to 2020–23, a notice of violation issued May 31, 2023, and a prior July 12, 2023 Chesapeake Bay approval whose conditions—including floodplain compliance and mitigation—were not met before the permit expired. Mike Wilson, section chief, Stormwater Resource Protection, told the board the structure was built in the RPA and that required deadlines had been missed. “The main issue is that they built the structure in the RPA,” Wilson said. Kevin Cameron, the owner, acknowledged the delays and said the property could accommodate the plantings staff requested: “I think it could hold all the necessary plants that they're asking for,” he said.
Applicant representatives said they had begun mitigation and compliance work before the hearing. Agent Chase Grog of LandTech Resources said the Camerons had posted earlier surety and had planted 12 trees ahead of the meeting; he asked the board to allow time to finish required modifications, provide elevation certificates and finalize mitigation. Grog proposed a contractor’s letter saying the work could be completed within 90 days; the board approved a July 9, 2025 deadline in the amended motion.
For the Kingsmill single-family dwelling (CBPA-24-0069), applicants added two small rock-garden BMPs and an expanded mitigation plan after the board left the matter open at a prior meeting. Donald Davis, a land surveyor representing the builder, described the rock gardens as 30 sq ft surface areas with subsurface void space intended to accept roughly one inch of runoff per state standards and to supplement the required plantings. Board members and staff said the additional measures were an enhancement to mitigation and conditioned approval on the submission of installation verification from a qualified professional.
What the approvals require next
All approvals require the applicants to secure any federal, state and local permits that apply, record affidavits at the WJCC courthouse where required, and meet the timelines and sureties set as conditions of approval. Several cases included a 12-month-permit-expiration convention: most exception approvals will become null and void if construction has not begun by April 9, 2026, unless an extension is requested six weeks before expiration. The wetlands permit has a three-year expiration (04/09/2028) and a six-week deadline to request an extension.
Meeting context and significance
The boards handled primarily property-level requests—shoreline stabilization, residential additions, accessory structures, and minor site improvements—using the Chesapeake Bay preservation ordinance (James City County Code chapter 23) standards. The Osprey Drive case illustrates enforcement consequences for construction done without permits and how the board can condition after-the-fact approvals on mitigation, surety, and floodplain compliance. For each approved exception staff stressed that state and local permits and recorded affidavits remain prerequisites to building permits or final certification of occupancy.
The boards adjourned after routine board business; no meeting is scheduled in May, the chair said.

