County opens overlay bids; awards federal project to Knife River pending state review

3652842 · May 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Pipestone County opened bids for two road overlay projects — a federally funded job and a state-aid project in Edgerton. Knife River submitted the low federal bid and the board voted to award contingent on state review; state-aid work will be awarded to the lowest accepting bidder.

Pipestone County opened sealed bids for two overlay projects and later voted to award the larger federal job to Knife River, contingent on required state review. The smaller state-aid overlay in Edgerton will be awarded to the lowest accepting bidder.

The bids matter because federalized projects trigger additional federal compliance and review; awarding contingent on state review allows the county to proceed while satisfying federal oversight needs, county staff said.

At the public bid opening, the county received three bids on the federal overlay: Knife River of Sauk Rapids ($2,639,404.49), Donex Incorporated of Prinsburg ($2,647,683.67), and Central Specialties of Alexandria ($2,785,048.15). County staff noted their engineer’s estimate was $3,125,563.40.

For the Edgerton state-aid overlay the county received two bids: Donex Incorporated ($118,845.20) and Central Specialties ($119,636.00); the county’s estimate for that job was $72,209. County staff explained they separated the projects so the smaller town work would not be federalized and require ADA and sidewalk upgrades.

After reviewing bids, county staff recommended awarding the federal contract to Knife River subject to state review of required federal documents (EEO and related forms). The board voted to award contingent on that review. For the Edgerton state-aid project, the board approved awarding to the lowest accepting bidder; staff said Donex is the low bidder but that bidder may withdraw if denied the federal job, in which case the county would offer the contract to Central Specialties.

County officials said the work is expected this summer; staff will follow up with contractors on scheduling and notify municipalities before pavement work starts.