Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Data Centers Ordinance topic
No spam. Unsubscribe anytime.
Board tightens rules for data centers and power generation — adds noise monitoring, setbacks and conditional‑use review
Summary
Frederick County amended its zoning code April 9 to define data centers, require environmental noise impact assessments and monitoring, impose a minimum 200‑foot residential setback, limit generator testing to weekdays, and make data centers conditional uses in several industrial districts.
Get email alerts on the Data Centers Ordinance topic
No spam. Unsubscribe anytime.
The Frederick County Board of Supervisors on April 9 adopted an amendment to Chapter 165 of the county code to regulate data centers and separate power generating facilities from transmission/distribution utilities.
Key provisions of the ordinance amendment: - Data centers are defined as premises where computers, telecommunications and related equipment primarily process, store or transfer information, including associated infrastructure such as generators or substations. - Data centers in B‑3 (Industrial Transition), M‑1 (Light Industrial) and M‑2 (Industrial General) zoning districts will require a conditional use permit; the TM (Technology/Manufacturing Park) district remains an allowed use where that district exists. The change removes automatic by‑right approval in the listed districts and adds legislative review. - A 200‑foot minimum setback is required where a data‑center site adjoins residentially zoned property (including RP, R4, R5, MH1 and RA); staff emphasized this is a minimum and site‑specific approvals may require larger buffers. - A category C full screen buffer is required where data‑center property adjoins residences. - Applicants must submit an environmental noise impact assessment prepared by a qualified acoustical consultant at the time of rezoning or conditional use permit application; monitoring must be performed at the property line. A baseline noise model is required prior to legislative approval, with post‑construction verification 12 months after certificate of occupancy and subsequent five‑year updates; changes or expansions will trigger new assessments. - Generator cycling and testing is limited to Monday–Friday, 8 a.m.–5 p.m. The ordinance also specifies that on‑site mechanical equipment should be located and screened to limit off‑site noise. - Power generating facilities (solar, wind, natural gas, diesel, etc.) were separated in the code from transmission/distribution utilities; many generation facilities will require conditional use review to allow case‑by‑case consideration of impacts and infrastructure needs. - Site assessment requirements for data centers include water‑use estimates; staff noted technology has reduced water demand on many newer designs, but water use must be evaluated case by case.
The planning commission recommended approval after a February public hearing; the board received public comments April 9 urging stricter setbacks, stronger air‑pollution and e‑waste management measures, and more rigorous water‑use limits. Staff and the board said the ordinance reflects lessons from nearby jurisdictions and a Commonwealth white paper and supplements those with noise‑study standards recommended by an acoustical consultant.
The board approved the ordinance amendment by unanimous vote. Roll call: Supervisor Jewell — aye; Supervisor Dunn — aye; Supervisor Wells — aye; Vice Chair — aye; Supervisor Lockridge — aye; Supervisor Leerro — aye; Chair — aye.
Ending: The ordinance now requires developers to seek conditional use review and meet technical noise and siting standards; staff said they will continue to monitor best practices and suggested the county could pursue additional e‑waste or air‑quality measures separately if needed.
