Board approves Vint Hill self‑storage complex with conditions limiting vehicle and RV storage
Summary
Supervisors approved a special exception to allow construction of a self‑storage complex at Vint Hill with an aggregate footprint over 50,000 sq ft, subject to conditions restricting storage to household goods, limiting vehicle/RV storage, and requiring window glazing and lighting controls to reduce neighbor impact.
Get email alerts on the Commercial Development Vint Hill topic
No spam. Unsubscribe anytime.
The Fauquier County Board of Supervisors approved a special exception 4-0 on May 8 permitting construction of an indoor self‑storage complex at Vint Hill with an aggregate building footprint of just over 107,000 square feet. The parcels are at the corner of Kennedy Road and Edmore Court in the New Baltimore Service District and total approximately 7.8 acres.
Staff told the board the rezoning amendment approved in 2018 allows the use in PCID but requires special‑exception approval for structures or groups of structures serving the same enterprise with an aggregate footprint exceeding 50,000 square feet. The applicant proposed six buildings (one two‑story office/climate‑controlled building plus five exterior‑access storage buildings), two gated entrances from Edmore Court, perimeter landscaping, and estimated business operations of two employees and about 20 customers per day with 24/7 gated access for unit renters.
The planning commission recommended approval with conditions to limit storage to personal property and household goods (consistent with the zoning ordinance), to prohibit indoor or outdoor storage of RVs and motorized equipment, to require upper‑story window glazing to reduce light pollution, and to limit visible interior lighting to office hours. The Vint Hill Conservancy provided a letter of support; the conservancy’s approval will be required before site‑plan release.
Planning staff estimated about 44 vehicle trips per day for employees, customers and deliveries. The board confirmed that additional conditions imposed by the conservancy or required at site plan stage would be addressed later in the review process. The motion to approve included the planning commission’s recommended conditions and passed unanimously.