Council approves Centennial Park Phase 2 Creekside Improvements at proposed GMP of $609,024
Summary
Council authorized phase 2 guaranteed‑maximum pricing for Centennial Park Creekside improvements, awarding phase work to the contractor under the CMAR agreement; work will begin after the July 4 celebration and includes ADA access, terraces and a PermaTrak boardwalk.
University Park City Council on April 15 approved the guaranteed‑maximum price for phase 2 of Centennial Park’s improvements, the Creekside Terraces, at a not‑to‑exceed amount of $609,024.
Shawn Johnson, parks and recreation director, told council the phase 2 scope includes terrace overlooks along Turtle Creek, upgraded fencing and entrances, widened ADA‑compliant paths and a durable PermaTrak…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat