Lynn City reports near-completion of wastewater upgrades, outlines $275M CSO and treatment financing and budget impact

3605032 · April 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At a Lynn City Water Commission meeting on April 1, staff reported that the wastewater treatment plant upgrades are nearing completion and described the planned financing for that work and a wider combined-sewer-overflow (CSO) program.

At a Lynn City Water Commission meeting on April 1, staff reported that the wastewater treatment plant upgrades are nearing completion and described the planned financing for that work and a wider combined-sewer-overflow (CSO) program.

Commission staff said the most recent contractor invoice — listed as invoice number 42 — was approximately $1.3 million for February and that the overall wastewater project is about 94% complete. “Everything seems to be moving, fairly well ahead,” staff said. The staff update said the commission has not yet started paying debt service through the Clean Water State Revolving Fund (SRF) program; once the contract is complete the SRF financing is expected to be split…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans