Water fund adds $200,000 roof replacement and advances Keys Grove reservoir contribution
Summary
The Water Fund budget includes an amendment to add an estimated $200,000 commercial roof replacement for a city water facility and continues funding for the Keys Grove reservoir; staff described the reservoir financing plan and capital priorities.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
City staff asked the Budget Committee to amend the Water Fund capital budget to include an estimated $200,000 commercial roof replacement at a water treatment facility after recent leak-related damage to electrical cabinets and control equipment.
Staff explained the rooftop on a building that houses a programmable logic controller (PLC) had begun leaking; temporary repairs were completed but new leaks have appeared. Presenters said several roofers inspected the flat roof and advised replacement because the roof is near the end of its service life. Staff proposed increasing Water Fund capital outlay from $5,000,945 to $6,000,145 and reducing contingency by a like amount; staff said the fund—s projected cash carryover supports the amendment.
The presentation also reviewed larger, planned water capital work: construction of the Keys Grove reservoir (a $3,000,000 project noted in the urban renewal allocation), new wells, generator replacement, treatment-plant upgrades, northwest distribution pipeline replacements, and water-loss reduction measures. Staff described a financing approach combining debt proceeds and previously budgeted ARPA or grant funds for the 3,000,000 reservoir and noted that long-term debt schedules are set against maturing obligations in 2028 and beyond.
Committee members asked about timing and whether immediate roof replacement would mitigate damage risk; staff said short-term repairs were holding but that recent rainfall and ponding near walls increased urgency. Staff asked the committee to include the roof project in the current fiscal-year budget so bidding and procurement could proceed in the winter construction window.
The committee adopted the overall budget as amended, which includes the water-fund capital adjustment; staff said the roof project will be added to the capital project list and identified in the published budget documents.