Josephine project manager reports steady progress on community center; staff accept monthly update
Summary
AGCM project manager reported that interior sheetrock is complete, storefront windows are installed, and schedule and budget remain stable; the council accepted the monthly AGCM report and asked staff follow-ups on potential flooring concerns and inspection roles.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
City project manager Ethel provided the May update on the new community center and public-safety annex on May 12, reporting that interior sheetrock is complete, storefront frames and windows are installed, weather barrier is complete and taping and mudding are underway.
Why it matters: The building houses public safety functions and community space; progress and any unforeseen construction issues could affect the opening schedule and FF&E staging. Staff said the overall project schedule and budget remain the same and that only one small change order is expected for power outlets and IT conduits.
Ethel said forthcoming work includes ceiling framing and interior finishes, driveway paving and final interior finishes; roll-up doors had been installed and FF&E deliveries were underway. She noted one area of concern: flooring in the kitchen area may be affected by persistent moisture near an ice maker, and staff are monitoring adhesive performance and will determine if remediation is required.
Council members asked clarifying questions. One councilmember asked about Atlas Inspections’ role; staff said Atlas is a contracted inspector for the city that conducts mechanical and general inspections. Staff also confirmed MCA is the vendor for police interview-room cameras and audio. Council voted to accept the AGCM report, 3-0.
Next steps: Staff will continue monitoring the flooring issue and report back if remediation or a change order is required; the project remains on schedule according to the monthly update.