Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Flood Protection topic

No spam. Unsubscribe anytime.

Virginia Beach officials report progress on $700M flood program and defend planned Pleasure House Point wetlands restoration

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff and the Flood Prevention Bond Referendum Oversight Board told council they will keep projects on schedule despite permitting and utility coordination delays, and defended restoring wetlands at Pleasure House Point after public concern and a notice of appeal.

Jeff Waller, chairman of the Flood Prevention Bond Referendum Oversight Board, told the Virginia Beach City Council during an informal session that the city’s flood protection program—funded by the 2021 bond referendum—consists of seven master project areas and 21 identified projects plus supporting work, and that the board will report to council quarterly as required by the resolution creating the oversight board.

The program is advancing on multiple construction and design fronts but faces expected third-party delays, city and Jacobs Engineering staff said. Jacobs program manager Alicia Pico told council the program timeline runs from 2021 to about 2032 and that staff have transitioned multiple projects from early engineering into 30% and higher design phases. "We have made great progress," Pico said, while warning that environmental permits and utility coordination remain the primary external risks to schedule.

Why it matters: The bond-backed flood program is meant to reduce flooding across multiple Virginia Beach watersheds; council members pressed staff for clarity about stalled projects in the southern city and about a contentious wetlands-restoration plan at Pleasure House Point that opponents say will remove mature trees.

Most important details - Program scope and spending: Waller said the referendum identified 21 projects; staff reported through February the program has spent about $107.2 million to date and that roughly $700 million of program cost remains at planning level. Jacobs reported a program variance that has remained about 5–6% of the total since the program began. - Project status highlights: Windsor Woods tide gate, Bow Creek Stormwater Park (sections), Eastern Shore Drive bundle, and several drainage-improvement projects are at 30%–90% design or entering pre-construction; Lake Bradford/Chubb Lake design-build has a notice of intent to award posted. Jacobs said the Windsor Woods/Princess Anne Plaza/Lakes “mega bundle” will be baselined in June, at which point more planning numbers will convert to baseline estimates. - Delays and risks: Pico and Jacobs described permitting delays affecting Back Bay marsh restoration, Elizabeth River floodplain restoration, Pungo Ferry Road improvements and the Sandbridge Newbridge intersection; staff said they are increasing outreach with regulators and the public. Utility coordination remains difficult in some corridors, but contractors and staff have mitigated several schedule impacts through active collaboration. - Supply-chain impacts: Jacobs briefed council on commodity and lead-time trends. Pico said base-metal prices have generally eased, concrete escalation has moderated (from near 10% a year prior to about 6% year-over-year), steel conduits are down, while plastic pipe and construction labor remain elevated. She flagged long-lead items for pump-station projects: emergency generators (currently 55–90 weeks), motor control centers (around 50 weeks) and switchgear (about 75 weeks).

Pleasure House Point wetlands restoration and wetland-banking dispute Council members and staff spent significant time on the Pleasure House Point wetlands restoration plan, which is intended in part to generate tidal-wetland mitigation credits tied to the flood-protection projects.

Council member Henley raised concern that projects in the southern part of the city are “stuck in the environmental permit stage” and specifically pressed for clarity on the Back Bay marsh restoration. "This just doesn't make sense to me, given all of the studies that we had done preliminarily and all the support we had had from all the agencies preliminarily and now to have it stopped," Henley said. Staff told Henley they expect a formal briefing to council in mid-April on the marsh-restoration permitting issues.

Director Hansen of the Department of Public Works (identified in the session as the staff lead on wetlands and mitigation strategy) explained the city’s approach to wetland credits and why staff proceeded with a restoration at Pleasure House Point rather than attempting to buy credits from an existing bank outside the Lynnhaven River Basin. Hansen said permitted wetland credits are tied to a specific hydraulic unit code and to a project permit; credits must be the right type (tidal wetland credits) and be available at the time the city applies and is permitted. "Those credits… are tied to a permit. They're tied to a specific use," Hansen said, adding that banks in other basins had not produced a reliable path when the city needed certainty.

Council member Josh Schulman outlined outreach and mitigation efforts connected with Pleasure House Point, saying city staff coordinated tree-salvage events and community communications and that volunteers helped recover trees and wetland grasses prior to construction work beginning. He said staff coordinated with Parks and Recreation, environmental nonprofits and neighborhood representatives to reduce wildlife impacts.

Legal status: Mark (city staff in legal/administrative role) told council the city received a pro se notice of appeal from a single citizen related to the Pleasure House Point permit. "We've received a notice, but we haven't received a petition," Mark said, explaining that a petition must follow within 30 days of the notice and absent a petition filed to date he did not see anything that would interfere, in the short term, with proceeding under the existing permit.

Council reaction and next steps Multiple council members urged additional public engagement and clarified that, in their view, the Pleasure House Point restoration will produce environmental benefits and provide mitigation credits necessary for other flood projects. One council member noted the challenge of finding 12 acres of suitable waterfront land for a restoration project if the city attempted to buy replacement acreage on the open market.

Staff commitments included a planned April briefing on the Back Bay marsh permitting issues, notification to council when board meetings occur in a member's district, and continued outreach materials already posted to the city's flood-protection website (Jacobs and city staff said the program has produced roughly 30 explainer videos and construction photos for public viewing).

What council did: No ordinance or final action was taken on the projects during this informal session. The oversight board reiterated it will provide quarterly reports as required by the creating resolution. Staff indicated the Windsor Woods/Princess Anne Plaza/Lakes bundle will be baselined in June and that the Lake Bradford/Chubb Lake design-build notice of intent to award has been posted.

Ending Staff and board representatives offered to continue district-level briefings and to invite council members to site visits as projects reach visible construction milestones. Jacobs and the Flood Prevention Bond Referendum Oversight Board will return with the next quarterly update and with a formal presentation on the Back Bay marsh permitting issues in mid-April, according to staff.