The committee approved a contract with Casco Technical Services Inc. to replace dated computerized HVAC controls at 601 Morris Street; staff said the controls were about 20 years old and piecemeal repairs had already been required.
Get email alerts on the Facility Maintenance topic
No spam. Unsubscribe anytime.
The City of Charleston Finance Committee on May 5 authorized an agreement with Casco Technical Services Inc. to upgrade computerized HVAC controls at 601 Morris Street.
Committee staff said the building’s control system is roughly 20 years old and has required ad hoc repairs; the approved work will replace the building’s central control “brains,” install new sensors throughout the facility and improve overall HVAC performance.
Mister Michaud, staff member, described the work as an upgrade to “the brains of the HVAC system” and said staff previously completed a one-room repair earlier this year. He told the committee the contract was procured through a competitive process that used estimated labor-hour benchmarks because the precise scope was not fully known at bid time.
A motion to approve the resolution was moved and adopted by voice vote with no recorded opposition. Committee members asked no further detailed questions during the item. No statute, ordinance, or external funding source was cited during the discussion.