Administrator details park, field and infrastructure projects and applies for recreation grant
Summary
Borough Administrator David briefed the council on multiple projects including a local recreation-equipment grant (deadline Jan. 31), salt-dome and turf-field work, traffic-light preconstruction schedule, Grove Street Park timing and a planned HR/timekeeping system launch in mid-February.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
At the Jan. 21 meeting the borough administrator summarized a series of capital and infrastructure projects and asked the council to authorize a recreation-equipment grant application with a Jan. 31 submission deadline.
Administrator David said the grant application would cover lighting improvements at Bruceville Commons and recommended the council add a resolution at the end of the agenda to authorize the application. He asked for council consensus to proceed; council members signaled support.
David reported project updates: the Department of Public Works salt dome panels arrived and are ready for contractor assembly after the concrete cure period; the municipal field turf project is slated to begin preconstruction work with expected turf installation in March and completion in early April, including ADA-compliant dugouts; the traffic-light preconstruction meeting notes were included in the agenda and field construction is scheduled to begin in the latter part of summer with the new light operational by November. Grove Street Park — including the dog park and skate park — remains on hold until frost leaves the ground; the administration said they would open the park at the earliest suitable date in April and indicated underground water-feature work requires frost-free conditions.
On facilities and design, David said the borough engaged an engineer for tennis-court post-tension concrete design and proposed moving that work to the special-projects engineer to preserve the primary engineering firm's focus on streets and utilities. The council discussed directing the special-projects engineer to begin work on the tennis-court design.
David also reported progress on a fiber installation tied to a county sheriff-services agreement and ongoing coordination with county counsel and IT staff. He told the council he would investigate New Jersey Infrastructure Bank (iBank) financing for sewer and storm-sewer projects; the administrator noted iBank loans often carry low interest (about 1%) and sometimes include principal forgiveness, which could relieve pressure on bonds and the operating budget.
On personnel systems, David said the borough will launch an electronic human-resources and timekeeping dashboard to replace paper PAFs and time-off requests. The administrator proposed launching the system for the pay period starting Feb. 16; the police department will continue using its timekeeping system with reports likely integrated into the new platform.
Council members asked clarifying questions about opening park features separately, the salt-dome timeline and change-order concerns on prior capital projects; council discussion referenced Colliers (the borough's consultant) and an intent to limit change orders by assigning some work to a special-projects engineer.
No formal motions were required for most of these informational items; the administrator asked for and received council consensus to add the recreation-grant authorization as a resolution for formal approval.