Staff reports minor TxDOT comments, utility coordination for Street Bond Package 3; Silver Saddle sequencing planned
Summary
Staff said Street Bond Package 3 was resubmitted to TxDOT with minor comments, that utility companies (CenterPoint Energy, Comcast) are reviewing relocation impacts on Silver Saddle and Parrish/Owen Parrish, and that staff plans to sequence Silver Saddle first pending utility schedules.
Get email alerts on the Street Bond Package 3 topic
No spam. Unsubscribe anytime.
City staff updated the council on Street Bond Package 3 and said they resubmitted plans to TxDOT after addressing minor comments. The resubmittal included tie-ins from concrete to asphalt and drainage calculations intended to avoid impacts to existing drainage infrastructure.
The update matters because the bond package work requires utility coordination and some relocations. Staff said CenterPoint Energy flagged concerns about shallow gas lines in the older neighborhood around Owen Parrish and Silver Saddle and that Comcast also identified facilities that would require adjustment or relocation. Staff is seeking timetables from utility companies before finalizing an advertisement and construction sequence.
Staff said the plan is to sequence Silver Saddle first and then move into Parrish; a construction advertisement period would follow confirmed utility schedules. Staff estimated that some utility relocations could take six to seven weeks once scheduled but said those schedules had not been confirmed in the meeting.
Angleton ISD reviewed designs affecting a special-needs school parking lot and staff said those ADA-related parking adjustments were coordinated in the current designs. Councilmembers asked for a refreshed look at the broader bond package (including previously discussed streets and Western Avenue exhibits) so council can evaluate priorities ahead of budget discussions.
Staff said they will return with confirmed utility schedules and more details on sequencing and timing for construction advertising, contract award and project starts.