Angleton hears timeline, budget and design changes for King Municipal Operations Center
Summary
Architect Brent Bowles told the City Council the King Municipal Operations Center design is 95% complete, Teal Construction is preparing bid solicitations and the team expects a guaranteed maximum price and a council workshop in May before possible permitting and a 30–45-day timeline to break ground.
Get email alerts on the Municipal Operations Center topic
No spam. Unsubscribe anytime.
Brent Bowles, an architect with IAD Architects, told the Angleton City Council the King Municipal Operations Center project is on schedule and remains "very much on budget." He said the design team submitted a 95% design package to Teal Construction, the construction manager at risk, and the contractor is soliciting bids from subcontractors and vendors to assemble a guaranteed maximum price (GMP).
The update matters because the GMP will determine whether the council can approve construction quickly and move to permitting and site work. Bowles said staff expects to receive the compiled GMP numbers in May, hold a workshop with staff to vet bids, and bring a final package to council in mid-May.
Bowles summarized recent design changes meant to increase flexibility and reduce cost: removing hard office walls to create flexible workspaces, slightly reducing office square footage, adding an extra set of workdays into the operational schedule, and carrying forward locker rooms, a training/multipurpose space and other program elements. He said "we did take some square footage out of the office portion" and the changes are reflected in the 95% documents now at the contractor.
City councilmembers asked several logistical and durability questions. Bowles said the new building footprint is south of the existing municipal operations facility so the current bays can remain in use while the new building is constructed; the existing front portion of the old building was already demolished to make room for the new entry and paving. He also said the architect’s specifications call for split-face CMU masonry accents on the north facade, durable LVT (luxury vinyl tile) in corridors, ceramic tile in wet areas, and carpet only in the conference room and offices. On roofing, Bowles confirmed the drawings specify a standing-seam metal roof.
Bowles said his contract does not cover the physical move of equipment and materials from the old bays to the new facility; staff will handle that transfer after occupancy. He also said the project team plans to review bids with staff before presenting a final GMP to council and hopes a council approval in May would allow permitting and then breaking ground roughly 30 to 45 days later.
Councilmembers pressed on lifecycle and finish choices, especially given Angleton’s Gulf Coast environment. Bowles said finish lifespans depend on vendor selections and bidding; the design includes durable exterior products and an appearance palette intended to align with city branding. He also said the contractor will vet vendor bids to ensure consistency across trades.
The council received the update and asked staff to return with the GMP and a formal presentation from Teal Construction when those numbers are compiled.
Bowles said he would return to council with the finalized numbers and a recommended GMP once Teal completes bid solicitation and vetting.