Council hears updates on Street Bond Phase 3: North Parrish redesign and Silver Saddle repaving

3512694 · January 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff described proposed curb-and-gutter reconstruction for North Parrish to meet city standards (roadway lowering, ADA access and parking changes) and a narrower repaving/realignment for Silver Saddle to preserve trees; combined conceptual cost is approximately $3.4 million for both projects.

Angleton City Council on Jan. 14 heard progress updates on two street-bond projects in Phase 3: North Parrish near Hamilton ISD and the Silver Saddle cul-de-sac off Bronco Bend.

Staff said North Parrish will be converted from an elevated roadway with roadside ditches to a standard curb-and-gutter section. Because the ditches will be removed, the roadway grade will be lowered between 1.5 and 2.5 feet to maintain positive drainage. The proposed cross section includes a 28-foot roadway with 6-inch curb and gutter, 24-inch storm sewer, and a 5-foot sidewalk on the east side; staff described special grading and a rollover curb near a special-needs school parking lot to preserve ADA access and maximize front-door parking.

Staff acknowledged the street'level changes will require temporary traffic controls, short-term driveway work, and a low-profile barrier during certain phases to protect vehicles and pedestrians. The estimated paving and drainage budget for North Parrish was approximately $2.8 million. Staff said additional coordination with Angleton ISD and stakeholders is planned.

Silver Saddle is a narrow residential asphalt street that narrows to about 10— feet in places where only one car can pass. Staff proposed an 18-foot elevated asphalt section with black-base stabilization to preserve existing trees by shifting the roadway alignment in places. Staff said they walked the neighborhood and discussed options with residents; the conceptual Silver Saddle estimate was in the low hundreds of thousands and staff rounded the pair of projects to a combined total of about $3.4 million for the two streets.

Council asked staff about timeline and TxDOT approvals for tie-ins where state right-of-way is involved; staff said they submitted plans and will follow up with TxDOT on review timing. Staff said Silver Saddle could be quicker to complete than Parrish because it is a smaller project and may come in under estimate.

No action was taken; staff will continue design refinement, TxDOT coordination and resident outreach.