Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Facilities Renovation topic
No spam. Unsubscribe anytime.
Board awards $248,800 Davidson Middle Academy renovation package
Summary
The board approved awards totaling $248,800 for the first phase of renovations at Davidson Middle Academy, splitting work between flooring and painting contractors.
Get email alerts on the Facilities Renovation topic
No spam. Unsubscribe anytime.
The Southgate Community School District Board of Education voted May 13 to approve the summer 2025 renovation package for Davidson Middle Academy, awarding contracts totaling $248,800.50 for the project’s first phase.
Representatives from Real Point and district staff described the work as phase one, covering offices, the multipurpose area (gymnasium and cafeteria) and painting throughout the building. The district received six sealed bids; after post‑bid interviews, the presenters recommended Cohen’s Commercial Flooring and R & M Painting.
The contract awards break down as $157,938 to Cohen’s Commercial Flooring and $55,862.50 to R & M Painting, with the total project amount listed at $248,800.50. Presenters said the contracts will use the AIA A105 form and that legal counsel reviewed the documents. The board moved and approved the package without recorded questions or amendments.
The district said post‑bid interviews were conducted with the firms that submitted proposals and that staff and legal counsel reviewed contract documents before recommendation. No timetable for construction start or completion was recorded in the transcript.

