Administrator outlines engineering updates: grants, EV chargers, PSE&G gas-main work and sewer project applications

3510214 · February 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The borough administrator reported on pending permits and applications — DEP review for a restoration permit, upcoming Sand Volleyball Court construction, NJDOT road projects, grant applications for Williams Field lighting, EPA sewer grant work, EV charging installations this spring, and a PSE&G gas main replacement starting in March.

The borough administrator gave an engineering update at the meeting covering multiple ongoing and proposed capital and grant-funded projects.

Items discussed included a pending permit application to the New Jersey Department of Environmental Protection for the French Restoration Project (submitted Jan. 17), a pre-construction meeting for a sand-volleyball court with construction expected mid- to late March, and engineering work to prepare construction documents for two joint NJDOT road-improvement bids (Roslyn/Monroe/Marion and a second set including Steuben, Clinton, Linwood, Maple and Roosevelt).

The borough has submitted two grant applications for a Williams Field lighting project: one to the Local Area Recreation Improvement Program (LARIP) for $100,000 and another to Green Acres for $294,500. The administrator said the Green Acres grant is a 50% matching grant and the borough is seeking additional funding to offset the required local match.

Engineering is preparing construction-management proposals for the Main Street Improvement Project, and the borough has prepared application materials requested by a grant writer for an EPA sewer project on Pine and Neuse. The transcript records notice that Bergen County intends to pay for improvements on Milford Avenue from River Road to the Dumont line as part of its 2026–27 road program; the borough indicated preliminary work would proceed in advance of that county program.

The administrator said installation of electric-vehicle charging stations is scheduled to begin this week with chargers set in place by March and powered by April or May; locations listed were Borough Hall, the library and Knights Field. The PSE&G gas-main replacement project — referenced in prior meetings — is scheduled to begin in March, starting with Webster Drive, Pearl Lane and Hershefeld Place and continuing to Harrison Street, Grand Street, Pershing Avenue and River Road; the administrator said the work will take approximately three months and notices will be sent to affected homeowners.

Finally, the administrator reported the 2025 budget timeline is delayed roughly a month because revaluation information from the tax assessor arrived later than usual; introduction of the budget was anticipated on March 24 pending that data.

No formal votes were recorded on the engineering items during the meeting; council members and liaisons were asked to forward stakeholder contact information for a forthcoming community energy planning survey associated with a separate grant.