Engineer: galvanized water-service replacements one-third complete; Franklin Field bleacher work progressing

3509595 · February 5, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Borough engineer reported the contractor has completed about 104 of 298 planned galvanized water-service replacements (approximately 33%) and that work is underway on field bleacher and streetscape projects.

The borough engineer reported Feb. 5 that the contractor on the galvanized water service line replacement project (Phase 3) has completed service replacements at 104 of 298 properties, roughly 33% of the total, and has started work on Third Avenue with an estimated one to two weeks to complete that street.

Joe Byrne, the borough engineer, told the council the county road opening permit for Diamond Bridge Avenue was still pending as of Jan. 31. Byrne also updated the council on other capital projects: the Franklin Field press box and bleachers have been installed…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans