NDOT District 2 outlines project progress, safety tech and Metro study priorities in Fremont
Summary
NDOT District 2 staff reviewed completed and upcoming projects including the Highway 275 completion, Highway 30 relinquishment work, safety projects at Murray and North Bend, diverging diamond interchange planning and new safety technology such as sequential flares and drones.
Get email alerts on the Ndot District 2 Programs topic
No spam. Unsubscribe anytime.
NDOT District 2 staff on Thursday gave commissioners a district‑level program update that highlighted recent completions, ongoing maintenance and safety measures across eastern Nebraska.
Tom Gilmore, District 2 engineer, reviewed projects completed since the last meeting (including much of the Highway 275 corridor in District 2), near‑term maintenance work, and planned improvements such as a diverging diamond interchange at the 190th Street area and corridor safety projects near Murray and North Bend.
“We finished last fall,” Gilmore said of a Highway 275 segment, adding that NDOT staff and contractors had “done a nice job in pulling that together.” He described the agency’s use of a “2+2” construction approach on large corridor projects and said some sections will require full reconstruction rather than repeated overlays.
Gilmore also demonstrated new safety equipment NDOT has deployed: sequential flare devices to improve night‑work visibility and unmanned aircraft systems (drones) for bridge inspections, storm damage assessment and limited surveying. “We can just pop the drone out and get a close‑up,” he said, describing bridge inspections and post‑storm assessments that accelerate repair decisions and reduce lane closures.
The district update noted ongoing maintenance attention on high‑volume corridors in the Omaha metro area where traffic volumes can exceed 100,000 vehicles per day on segments of Dodge Street; Gilmore described programs to patch and preserve pavement so lanes remain serviceable while larger reconstruction projects are scheduled.
NDOT Director Vicky Kramer framed the district report in budget and statewide context, thanking District 2 staff and recognizing the role of federal partners. Kramer and staff also referenced the Metro Area emphasis study (the “MAPA” study) and related coordination for major metro corridors.
No formal commission action resulted from the district briefing; NDOT staff said the presentation would feed into programming and funding decisions for the department’s multi‑year program.