Portage County commissioners authorize CDBG application to rehabilitate Village of Manaway sewer system

3459352 · May 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At a May 1 meeting the Portage County Board of Commissioners approved filing an application to the Ohio Department of Development for a 2024 CDBG residential public infrastructure grant to rehabilitate the Village of Manaway wastewater collection system, with Portage County Water Resources agreeing to provide a 50% local match.

Portage County commissioners voted May 1 to file an application with the Ohio Department of Development, Office of Community Infrastructure for a 2024 Community Development Block Grant (CDBG) Residential Public Infrastructure award to rehabilitate the Village of Manaway wastewater collection system.

The request followed a public hearing during which a Portage County Water Resources staff member, identified in the record as Lisa, described the system as aging and failing. "We are working with water resources. The Village Of Manaway wastewater collection system, consists of 23,605 linear feet of 8 inch to 12 inch petrified clay pipe and 89 brick manholes that were installed in the late 19 sixties," Lisa said. She said the pipe's two-foot sections have separated over time, allowing root intrusion, groundwater inflow and infiltration, and that brick manholes have started failing.

The county's stated project scope includes cleaning and televising the vitrified clay pipe (VCP) sewers, pressure-grouting all joints to a specified pressure, cutting protruding service lines at the sewer main and sealing service connections, and sealing or replacing brick manholes where necessary. The presentation estimated construction costs at $1,490,505.49; a separate per‑foot rehabilitation estimate of about $60 was cited with actual cost contingent on the quantity of grout required.

Lisa said Portage County Water Resources has agreed to fund 50% of the local match; the county intends to request approximately $730,000 through the CDBG Residential Public Infrastructure program and identified $20,000 to cover regional planning administration. The board voted unanimously to authorize filing the application.

Why it matters: The Village of Manaway was described as a low- and moderate-income community with roughly 4,451 sewer connections; continued deterioration, the staff presentation said, contributes to sewer backups, higher wastewater treatment volumes and potential user surcharges if repairs are delayed.

Next steps: Board members directed staff to complete and sign the application materials and submit the grant application to the Ohio Department of Development. The hearing record does not name an engineer or contractor; no construction contract award or timeline beyond the grant application was adopted during the meeting.