911 staff present quote to separate tower power; commissioners discuss bids, costs and long-term radio options

3458600 · April 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trumbull County 911 staff reported a contractor quote of $91,800 to separate electric service for critical radio/tower equipment and an updated FirstEnergy portion of about $7,800; commissioners discussed procurement thresholds, bidding, and longer-term tower planning.

Stacy McDonald, 911 charge, updated commissioners that a vendor (Bechtel Controls) quoted $91,800 to separate electric service for the county’s tower equipment; the same quote had included an estimated $9,000 FirstEnergy charge that 911 later confirmed at $7,800, making the vendor total slightly lower.

Procurement and timing: Commissioners and staff noted that the county’s competitive-bid threshold (recently adjusted by statute) means a purchase around $91,800 will likely require a formal public bidding process. Board members cautioned that bidders’ prices are time-limited and that a bid exercise can add weeks to the procurement timeline. McDonald asked whether staff should proceed to solicit bids; commissioners said they needed clarity on whether the board wants to proceed and that staff should not initiate a formal bid without a clear directive because bids have limited validity windows.

Radio-system implications: Commissioners and public-safety staff discussed longer-term options: leaving the tower and restoring electric service, building a new county-owned tower at another site (cost estimates previously discussed in workshop conversation range from several hundred thousand to over $1 million depending on scope), or partnering with existing providers. Participants noted recurring rent and service payments on leased tower space and argued the county should consider a long-range radio and 911 infrastructure plan as part of capital budgeting.

Ending: Commissioners asked 911 staff to hold the vendor quotes and return with a procurement recommendation, timeline and options for longer-term radio infrastructure planning so the board can evaluate whether to fund separation work now or invest in a different tower solution.