Brighton gets progress update: water treatment plant ahead of schedule; Lutz Reservoir work to refill this summer
Summary
City staff reported the water treatment plant project is about 46 calendar days ahead of contract schedule with major equipment deliveries expected in May–June; Lutz Reservoir construction is also ahead and crews plan to begin refilling the reservoir in summer 2025.
City staff updated Brighton City Council on two major water infrastructure projects: construction of the new water treatment plant and the Lutz Reservoir project.
Scott Olsen, director presenting on the projects, and John (owner's representative) reported that the water treatment plant is trending 46 calendar days ahead of schedule and that excavation and major concrete work are complete. John said the team has consumed roughly 215,000 labor hours and is lining up large equipment deliveries: the softening reactors and chemical tanks were en route, and a crane operation to place large elements is planned for…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat