Brighton councilors question Cherry Meadows Park contract totals; city says change order was $21,900

3442911 · April 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Brighton’s finance staff presented the city’s monthly contracts report for March at the April 22 study session; a council question about Cherry Meadows Park focused attention on how the report displays contract numbers.

Brighton’s finance staff presented the city’s monthly contracts report for March at the April 22 study session; a council question about Cherry Meadows Park focused attention on how the report displays contract numbers.

A line in the report shows Cherry Meadows Park with a $2,000,000 figure, which council members read as a change order amount. Finance staff explained the report shows the new total under contract rather than the incremental amount added by a change order. City Manager Martinez told council the actual change order amount was $21,900.

Kyle Sylvester and other staff described the work behind the increase: unanticipated grading and drainage work after water raised on the site required a redesign so park pathways would not flood, and crews added soil amendments because the site had essentially been a gravel pit. Staff emphasized the $2,000,000 figure in the packet reflected the total contract value rather than a single $2 million change order.

Council members said the packet-level presentation led to confusion and thanked staff for the clarification. No formal action was taken during the study session; staff said they would continue reporting contract activity in monthly packets and are available to answer follow-up questions.