One‑campus building committee narrows Main Street changes, plans arsenic berming and issues turf bid without PFAS
Summary
The MSAD 51 building committee reported reduced plans for widening Main Street, a decision to relocate and berm arsenic‑contaminated soil off playing fields, formation of subcommittees for finishes/technology/budget, and release of bids for turf (PFAS‑free) and maintenance building.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Members of the MSAD 51 building committee reported to the board on Jan. 16 that the one‑campus design team has scaled back proposals to widen Main Street, addressed neighborhood parking concerns, set a remediation plan for arsenic in subsurface soils and issued project bids for turf and a maintenance building.
The committee said, after consultation with neighbors, the town police chief and architects, that major widening or turning‑lane work on Main Street will be minimized and that safety improvements will focus on crosswalks and signaling. Committee members said that widening the street could create safety issues and that the compromise prioritizes pedestrian safety and neighborhood concerns.
On site remediation, the committee reported arsenic was found on portions of the project site linked to prior land use (an historic orchard). The committee said it will move the contaminated material away from playing fields and create a berm; that berm will be repurposed for recreational use (sledding hill, etc.). A cost impact was discussed at the meeting but exact figures were not specified in the transcript.
The district announced that bids were released for the maintenance building and that a turf procurement will be issued with explicit specifications: turf systems must be PFAS‑free and use no performance infill (no synthetic rubber infill), favoring sand or other non‑PFAS ballast. Committee members said the turf bid language anticipates local restrictions and community expectations.
The committee also said it is breaking work into subcommittees (finishes, technology, mechanical, playground, budget/facilities) to manage a large volume of incoming decisions. Committee meeting dates were set through March and public notices for the project and bid opportunities were posted on the district website.
Board members and the public were invited to review materials and attend upcoming subcommittee meetings; the administration also noted soil testing and permitting requirements remain in progress.