Community center opening delayed after persistent drainage blockage; staff estimates 2—2 weeks for fix
Summary
Work to open Waterford's community center was delayed after crews found an obstruction in the drainage during routine punch-list work. Staff said a change order to reroute drains and cut floor will be required and estimated 2—2 to 3 weeks for the repair; June 1 remains a conservative target date.
Get email alerts on the Community Center Construction Delay topic
No spam. Unsubscribe anytime.
City staff told the council the community center's opening schedule has been set back after contractors discovered a blockage in the drainage line during punch-list work. Staff said an attempted hydro-blast did not clear the obstruction and the contractor now recommends cutting the floor and rerouting the drain near the water fountain and bar-area sinks.
The change order is pending; staff estimated the work will take about 2—2 to 3 weeks once authorized and that the delay may push the opening beyond the earlier hopes. City staff said June 1 remains a safe target date but they are still hoping the center could open earlier, perhaps by the end of the month. The speaker identified the affected fixtures as the sinks in the bar area.
Staff said crews had been addressing punch-list items from the reconstruction (tile chips and other blemishes) and the blockage was discovered during routine snaking of the drain. No new funding request or budget amendment for the repair was reported at the meeting; staff is awaiting the change-order paperwork to authorize work.
Council member questions focused on the likely length of the delay and whether additional issues were expected; staff replied the blockage was unexpected and they do not anticipate further problems.