The Waterford City Council adopted an update to the city's purchasing threshold, awarded a demolition contract for the old police substation and approved a budget amendment to fund the work, and authorized staff to release an RFP for Yosemite Boulevard frontage improvements. All votes were unanimous, 3-0.
Get email alerts on the Council Votes Contracts Budget topic
No spam. Unsubscribe anytime.
Waterford City Council on the evening of the meeting adopted Ordinance 2025-01 to align the city's purchasing thresholds with changes in California state procedures, awarded a demolition contract for the old police substation at 320 E Street, and authorized staff to solicit contractors for the Yosemite Boulevard frontage improvements project.
The ordinance (Ordinance 2025-01) was read for a second time and adopted to amend Waterford Municipal Code Title 3 (Revenue and Finance), chapter 3.08 (Purchasing), to reflect the state's five-year adjustments to contract-threshold levels. Council opened and closed the public hearing with no public speakers and approved the ordinance 3-0.
Separately, the council awarded the demolition contract for the old police substation (Project No. 2025-02) to Central Valley Demolition for a low bid of $29,890 and adopted Resolution 2025-14 to amend the fiscal-year budget and allocate funds for the demolition. Staff reported the total project cost is $39,890 and that funding will come from the city's general fund reserve (budget number 1010-110-7420). The motions passed 3-0.
Council also authorized staff to prepare and release a request for proposals for contractors for the Yosemite Boulevard frontage improvements (Project No. 2025-01). Staff said the improvements will run along Yosemite Boulevard from Eucalyptus Avenue to Rhine Way, fill sidewalk gaps, widen pavement where needed, add curbs and sidewalks, and install storm drainage including French drains under proposed sidewalks. The engineer's estimate for the project is $800,000; staff said the work will be funded by a state Active Transportation Program (ATP) grant and will not use general fund dollars. That motion passed 3-0.
Votes at a glance: - Ordinance 2025-01: second reading and adoption to amend Waterford Municipal Code Title 3, Chapter 3.08. Vote: 3-0, outcome: adopted. - Contract award, Project No. 2025-02 (Old Police Substation demolition): award to Central Valley Demolition, bid $29,890. Vote: 3-0, outcome: approved. - Resolution 2025-14: budget amendment to allocate funds for demolition (total project cost reported as $39,890). Vote: 3-0, outcome: adopted. - Authorization to release RFP, Project No. 2025-01 (Yosemite Boulevard frontage improvements): engineer's estimate $800,000, funded by state ATP grant. Vote: 3-0, outcome: authorized.
Council discussion and context: Council member Gutierrez, who said she serves on the library advisory board and is a longtime supporter of local libraries, welcomed the demolition as a step that will support broader community improvement and library plans in the area. Staff clarified that the demolition project was not included in the current fiscal-year budget and therefore required the budget amendment.
The council recessed to closed session at the end of the meeting to consider a personnel/labor negotiator matter under California Government Code section 54957.6.