Resident raises surface and aggregate concerns as committee approves spring paving program

3390684 · April 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

During the consent-agenda period, resident Blair Mizer urged the township to require smoother surfacing and finer aggregate for spring repaving in the Whittier Oaks area. Committee members responded that current specification choices reflect state and NJDOT mandates; the consent agenda including the road paving contract was approved.

A Hillsborough resident told the Township Committee on April 22 that recent repaving and milling in older subdivisions produced a bumpy, wavy finished surface and that the coarse aggregate used in some resurfacing projects can cause severe abrasions for bicyclists or children who fall on streets.

Blair Mizer, a Fernway resident of 49 years, described visible "wavy" lane striping and headlights that bounce at night on repaved sections, and urged the engineering department and contractor to avoid inconsistent lift depths and to specify a finer, more granular surface aggregate in residential areas.

Committeeman Lipani, who had earlier presented the township—s carryover paving schedule, replied that the mix used on recent projects is the material currently mandated in certain contexts by the State and by NJDOT and that some mixes include recycled components by state requirement. He acknowledged that milled finishes are often rougher to motorcycles and that modern resurfacing mixes in some cases have shorter life cycles than older pavements.

Lipani had also reported the immediate schedule for carryover 2024 road projects earlier in the meeting: Camden Road milling and paving slated for April 24–28 (weather permitting) and a tentative set of work for Murray, Starview, Ski Drive and Dogwood targeted to complete by May 19.

The consent agenda (items 1–9), which included the road paving contract described in the engineering report, was approved by the committee.

Why it matters

Surface texture and aggregate selection affect road safety for cyclists, motorcycles and children playing near the curb. The resident—s comments point to trade-offs municipalities face between contractor bids, state-mandated materials or processes, and local expectations for ride quality and longevity.

Clarifying details mentioned at the meeting

- Camden Road milling and paving: April 24–28 (tentative, weather permitting). - Murray, Starview, Ski Drive and Dogwood concrete/improvement and milling/paving: scheduled to begin April 25 with tentative finishing around May 19. - Municipal specification note: Committee response indicated the resurfacing aggregate mix in some projects reflects state/NJDOT mandates and recycled-content requirements; the committee member characterized this as outside the township—s choice in some cases.

Ending

Residents with concerns about a specific resurfacing job were encouraged to contact the engineering department; the committee approved the consent agenda and the roads listed in the carryover schedule will proceed according to the contractor timeline and weather conditions.