Council approves $500,000 change order for Midcal park dredging work
Summary
Council authorized a $500,000 change order to continue dredging and related work so the contractor can remobilize and complete excavation ahead of summer season.
Get email alerts on the Parks Contracts topic
No spam. Unsubscribe anytime.
The Riverside City Council authorized a $500,000 change order for dredging and related work at a city park project to maintain construction schedule and deliver recreational amenities for the summer season.
Parks staff said the change order is needed because revised information about excavation and material quantities required additional work so the contractor would not need to demobilize and later remobilize, which could delay summer operations and paddle-boat availability. Staff described removing about 10,000 pounds of material and other scope clarifications.
City staff asked for the authorization to avoid schedule slippage and the council approved the change order without public speakers on the item. The motion passed unanimously.
Staff said the contractor will proceed quickly so seasonal amenities are available; project administration will remain with the Parks and Recreation Department and standard contract monitoring will apply.