Council work session: City moves to advance Core 3A/3B and Richland Park reconstruction in CIP
Summary
Staff presented a draft 2026–2030 capital improvement program that prioritizes Core 3A/3B sewer and street reconstruction and two phases of Richland Park (Nicholas area) work, with design in 2026 and staged construction over subsequent years.
Get email alerts on the Infrastructure Reconstruction topic
No spam. Unsubscribe anytime.
City staff outlined a draft 2026–2030 capital improvement program during a May work session, proposing near-term design and staggered construction for Core 3A and 3B and new reconstruction phases in the Richland Park area. Staff said Core 3A would be roughly $5 million with design in 2026 and construction in 2027; 3B is planned for design in 2028 and construction in 2029 and estimated at about $5.3 million.
The plan pairs Core and Richland work in a flip‑flop sequence so crews can switch between zones and limit simultaneous disruption. “We’ll flip flop: we’ll do Core 3A, Richland 1, Core 3B, Richland 2,” staff said. Staff described the Richland projects as full reconstruction areas, similar to the Rushmore/Core work already underway. They noted the underground utilities in portions of Richland are “in very poor conditions” and said sewer video has documented multiple problem spots.
Staff described Phase 1 of Richland as focused on Nicholas (Nicholas Glenwyn, Maria Lane, Marine Drive, Patrician Drive and adjacent blocks), estimated at about $1.5 million, and Phase 2 covering adjacent streets. Sidewalks in the Richland area were reported as narrow (often 3–3½ feet) and pushed up by roots; staff said the plan calls for replacing sidewalks to current widths (five feet where required) and removing selected trees where necessary.
Council members and staff discussed sequencing and the city’s ability to finance simultaneous projects. Staff said they had run preliminary financial scenarios and believed the city could move forward with 3A and 3B, but that detailed cash‑flow and bond capacity numbers would be provided at the next meeting. Staff emphasized the schedule remains an estimate until final cost numbers are available.
The work session covered related items including Rushmore Phase 3 and other CIP entries; staff asked council members for direction on additions or deletions before finalizing the financial package for council consideration.
Ending: Staff will refine cost estimates and return to council with updated financials; design work for the first phases is slated to begin in 2026, with construction staggered through 2029 in the draft schedule.