CTE center nearing turnover; trustees receive detailed bond project update and summer schedule
Summary
The board received a detailed bond program update showing the Career and Technical Education (CTE) center on track for substantial completion June 15 with a public ribbon-cutting planned July 30, and progress reports on district renovations, transportation fuel center and athletic complex.
Get email alerts on the Capital Projects And Construction topic
No spam. Unsubscribe anytime.
District construction staff and the bond program manager briefed trustees on progress across Prop A/B projects and the district's $326 million bond program, reporting steady progress and several near-term milestones.
The Career and Technical Education (CTE) center is on track for substantial completion on June 15, 2025, district staff said, with furniture deliveries and move-in scheduled immediately afterward. The board was told the community open house and ribbon-cutting are planned for July 30, with a limited invitation walk planned July 29.
Project managers reviewed work at multiple sites: Creekside Elementary (final punch list and terrazzo remediation options), Lake Creek (HVAC commissioning items), the triplet campuses (112 bathrooms to be renovated this summer), and Montgomery High School renovations (teaching-wall installs and bathroom work). Construction staff said some items required close coordination because the work affects summer athletics, band and other programs.
At the transportation fuel center, crews are scheduled to pour concrete for fuel tank foundations; district staff said fuel tanks and canopy installation would follow once concrete cures. The CTE building's specialized labs — cosmetology, culinary, welding and an enclosed ambulance for EMT training — have long lead‑time equipment already procured and in many cases scheduled for installation the week of move-in.
Trustees were briefed on stadium/athletic complex timelines and seat-back planning; officials said steel deliveries for bleachers are projected in July, which tightens the schedule for an August substantial completion for the athletic complex. Staff said they will monitor delivery dates closely and coordinate summer schedules to avoid disruption to summer activities.
Overall, most bond projects are within budget and contingency for the work presented, the district reported; staff said they will continue to notify the board of any scope or budget changes discovered during summer work.