Martinsville accepts Wallace low bid for spring paving; city also opened sidewalk bids
Summary
Officials opened three sidewalk bids and later approved Wallace Construction’s low bid of $668,625.78 for a spring paving project covering about five miles; the council voted to fund the paving from city funds.
Get email alerts on the Infrastructure Paving Contracts topic
No spam. Unsubscribe anytime.
Martinsville city officials opened sealed bids for a sidewalk project and later approved a separate paving contract, awarding the spring milling-and-paving work to Wallace Construction as the low bidder.
At the bid opening, city staff read three sealed sidewalk bids received that day: Wallace ($970,509.98), Milestone ($1,994,335.05) and All Star Paving ($3,446,326.65). City staff then reported on a separate solicitation for a roughly five-mile paving program; the low responsive bidder for that project was Wallace Construction at $668,625.78. City staff said they had reviewed the documents and found them in order and recommended the council accept Wallace’s bid for the paving work.
A council member moved to accept the Wallace paving bid of $668,625.78; another council member seconded the motion. The council then voted with the result recorded as in favor and the motion carried. Later in the meeting a separate motion was made and seconded to pay for the paving from city funds rather than filing an insurance claim; that motion also proceeded.
The award covers the spring paving contract as presented; staff did not, during the public discussion, provide a detailed construction schedule in the bid-opening segment. The sidewalk bid openings were recorded for procurement and will be subject to subsequent contract review and award processes by city staff and council.