Fall River Housing Authority approves contract amendment, awards fire-alarm and completes Riley Plaza boiler project
Summary
The Fall River Housing Authority board approved an amendment to a state contract extending service dates and funding, accepted a certificate of substantial completion for a boiler replacement at George E. Riley Plaza, and awarded a fire-alarm replacement contract for D'Farrell Village.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Fall River Housing Authority board voted to approve Amendment No. 14 to a contract for financial assistance between EOHLC and the authority, extending the contract period from June 30, 2027, to June 30, 2028, and as presented at the meeting authorizing roughly $21,000,000 in funding under that amendment.
The board also accepted a certificate of substantial completion for a boiler replacement at George E. Riley Plaza noting work by Lona Plumbing and Heating Services was substantially complete on April 5, 2025. "This certificate of completion for boiler replacement at Riley Plaza" was moved for approval and the motion passed, as recorded in the meeting.
Separately, the board awarded the HUD-funded fire alarm system replacement contract at D'Farrell Village (Mass 6-3) to La Rossi Electrical Contractors for $68,300, a low-bid award announced during the modernization agenda item.
The authority described the Amendment No. 14 work as funding to replace failing gas lines and other state-site modernization items (award number O95192 and related formula funding awards were cited). The board member motions for the amendment, the certificate of completion and the contract award were each made and seconded in open session and approved by voice vote.
The board was told the amendment would formally appear on next month’s agenda for any additional approvals required by HUD or state offices; the executive director said memoranda of agreement with neighboring housing authorities would follow the board’s action if the board elects to proceed.
Board members did not record a roll-call tally in the transcript for each vote; the meeting reflected unanimous voice approval on the modernization items with Commissioner Burns absent.
The board’s action now sets the authority to proceed with the work and with submittals required by EOHLC and HUD as described in the packet.