Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Facilities Projects topic
No spam. Unsubscribe anytime.
Speedway board hears construction update; approves Stair Associates for Allison HVAC and boiler work
Summary
Board received detailed facilities progress updates on field, bleachers, maintenance building and HVAC replacements; authorized Stair Associates to design Allison Elementary HVAC upgrades and a boiler-plant replacement.
Get email alerts on the Facilities Projects topic
No spam. Unsubscribe anytime.
The School Town of Speedway board received a multi-site facilities update on May 13 and approved a contract with Stair Associates to design HVAC and boiler-plant replacements at Allison Elementary.
Facilities staff described steady progress on stadium and building projects: east-side visitor bleachers were nearing completion, the west-side bleacher concrete pad was formed with concrete scheduled to be poured the following day, and the maintenance building slab remained the gating item before overhead doors could be installed. District staff reported the field walk-through is complete and the track’s final asphalt layer has a 28-day cure period before surfacing can be applied. Presenters said work remains largely interior and underground at this stage, and that change orders have stayed below expected allowances.
Project C (the Ox Gym / Door 13 southeast high-school project) and site work are advancing but remain contingent on permit approvals. Presenters said the gas line has been relocated and the Speedway Water Works coordination on the water line relocation is pending; the district expects administrative comments back from the town and anticipates permits to follow. On building upgrades, administrators described plans to replace aging central rooftop and mezzanine HVAC systems at Allison with individual classroom units and smaller “pony” boilers to improve energy efficiency and control. The board approved an agreement with Stair Associates for engineering, document preparation, bidding and construction-phase services for the Allison work; administration named consultant Woody Holm as the project lead for Stair Associates.
Board members and staff framed the work as keeping projects on schedule and on budget; staff characterized the contingency as “healthy.” Several technical items were emphasized as dependencies: final administrative approval from the Town of Speedway, building-permit issuance (ILP), and utility relocation completion before major site work can proceed.
Stair Associates agreement (action) The board voted 5–0 to approve the agreement with Stair Associates to deliver engineering design, construction documents, bidding and construction-phase services for Allison Elementary HVAC upgrades (16 classrooms) and replacement of the gymnasium boiler plant. Administration said Stair Associates will prepare design options (mezzanine versus rooftop units, classroom wall units, updated control systems) and oversee bidding and construction phases.
Implementation notes and timeline details - East-side bleachers: described as nearing completion with the west-side pad formed and concrete scheduled to be poured soon. - Track: final asphalt layer poured; approximately a 28-day cure before surfacing is applied. - Maintenance building: block walls up; interior rough-ins for plumbing and electrical largely complete; overhead doors pending slab pour. - Project C / Ox Gym: site work permitted only after ILP/building permit; gas line relocation is complete; water line relocation coordination under way with Speedway Water Works. Administration expected administrative comments from the town by the Friday after the meeting, after which permits could be processed.
Staff characterized implementation risk for the Allison design and site projects as medium because of the dependency on town administrative approvals and utility relocations; change-order exposure was described as lower than originally estimated to date.

