Crew quarters near completion; commissioners flag EV chargers, parking controls
Summary
Staff reported the crew-quarters dormitory is about 91% complete and on track for possible August move-ins; commissioners raised questions about EV charging access, metering and resident parking controls.
Nancy Smith, airport manager, told the commission the crew-quarters project is about 91% complete and progressed roughly 6% in the last month. Work reported finished or near completion included parking asphalt, shingling, stairs and soon-to-be-completed concrete flatwork. Smith said an inspection and potential move-ins are expected in late summer.
Smith said a change order is anticipated for a one-foot sidewalk adjustment to accommodate two EV charging stations at the dormitory parking spaces. She told the commission…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat