Runway seal coat set for next week; tower rehab and hangar move‑in progress at Springdale Airport
Summary
City staff reported that runway grooving and crack sealing are complete, seal coating and interim markings will be done next week with final markings after a 30‑day cure; tower rehabilitation is underway in phases and a newly completed power hangar has a certificate of occupancy and will begin tenancy in May.
Springdale City airport staff told the Airport Commission on April 17 that key airfield projects are advancing and that the airport will undertake nightly seal coating and remarking of the runway next week.
Greg Collier, airport projects staff, said the runway rehabilitation and grooving work is complete and that crews have sealed cracks. He said seal coating will be applied in sections during night shifts next Monday through Friday and that markings necessary to reopen the runway (numerals and the centerline) will be installed as the work progresses. Collier said the contract calls for a 30‑day curing period after the seal coat before…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat