Runway seal coat set for next week; tower rehab and hangar move‑in progress at Springdale Airport

3284383 · April 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff reported that runway grooving and crack sealing are complete, seal coating and interim markings will be done next week with final markings after a 30‑day cure; tower rehabilitation is underway in phases and a newly completed power hangar has a certificate of occupancy and will begin tenancy in May.

Springdale City airport staff told the Airport Commission on April 17 that key airfield projects are advancing and that the airport will undertake nightly seal coating and remarking of the runway next week.

Greg Collier, airport projects staff, said the runway rehabilitation and grooving work is complete and that crews have sealed cracks. He said seal coating will be applied in sections during night shifts next Monday through Friday and that markings necessary to reopen the runway (numerals and the centerline) will be installed as the work progresses. Collier said the contract calls for a 30‑day curing period after the seal coat before the final reflective markings with glass beads are applied: “By the end of the week, we should have the full runway remarked and the full seal coat installed. After that point, we're gonna wait 30 days for that seal coat to cure out, and then we'll come back and put the final, final layer of markings on.”

Commissioners asked about timing for striping and reopening; Collier said the minimum markings to reopen will be in place during the seal‑coat work, with the full final markings installed after the curing period.

On the air traffic control tower rehabilitation, Collier said staff and city IT have begun pulling cabling and are awaiting delivery of parts and equipment. He said the plan is to renovate half the tower at a time so at least one operator position remains functional during construction.

Power hangar reconstruction has reached project closeout, Collier said. The city has received a certificate of occupancy and expects the tenant to begin operations in May; staff will proceed with grant closeouts and reimbursement requests for two state grants and one FAA grant associated with the project.

Airport operations staff reported on personnel and tenant items. James (surname not specified), airport operations staff, said a longtime employee’s last day is tomorrow and that the department is interviewing candidates. He also said staff are arranging a camera on Palgate and following up with tenants who are slow to pay.

During old business, commissioners received an update on a separate “guard” item related to hangar conversions and funding. City representatives said the issue has advanced to state leadership and that they expect additional information by the commission’s May meeting; no final state decision has been reported.

The commission opened the meeting with a routine motion to approve (the agenda or minutes was not specified) that passed on a voice vote; no roll‑call tally was recorded in the transcript.