The Kane County Board voted to approve special-use permits for two commercial solar energy facilities—Rutland East and Rutland West—after hearings in which the villages of Hampshire and Pingree Grove said the projects would set a long-term precedent and block future commercial development along Illinois Route 47.
Get email alerts on the Land Use Solar topic
No spam. Unsubscribe anytime.
The Kane County Board voted to approve special-use permits for two commercial solar energy facilities near Hampshire on May 13, approving a 40-acre Rutland East site and a nearby Rutland West site despite formal objections from the villages of Hampshire and Pingree Grove.
The petitions, filed by Rutland East Solar Farm LLC and Rutland West Solar Farm LLC and presented by project attorneys and landowners, sought special-use permits in the F (Farming) zoning district to allow commercial solar facilities on parcels designated Commerce/Employment in the county’s 2040 comprehensive plan. Board members followed recommendations from the zoning board of appeals and the county development committee and carried the motions to approve both applications with stipulated conditions.
The village of Hampshire, represented at the hearing by Mayor Mike Reed and Assistant Manager Malcolm (last name on record), urged the board to deny the petitions. Reed said the Rankin/Route 47 corridor “is poised to be a commercial/retail development” and warned the county that approving temporary (30-year) solar uses on major corridors would “create a precedent … and hinder the development of that corridor for at least the next 30 years.” Pingree Grove raised similar objections and noted the petitions “are not conforming with the Kane County 2040 Comprehensive Plan,” asking the board to reject the special-use permits.
Project representatives, including landowner John Milney and attorney Jack Franks, said the solar proposals meet state and local standards and had been redesigned to address access and future roadway connections. Franks said the projects were altered to “allow for the future extension of Sandwold Road from Big Timber Road to Reinking Road,” and that revisions reduced the development footprint so more land remains available along the frontage for possible future commercial uses.
Petitioners said the sites currently lack utilities and that local market demand for commercial development is limited; they described solar as a viable interim use that would be decommissioned at the end of its operational life. Project representatives confirmed the facilities are planned as community solar/utility-scale projects and said they will survey and repair any drain tiles affected during construction and will restore the land if the sites are decommissioned.
During board discussion members asked about landscape buffers, floodplain and drainage features along the southern boundary (identified during testimony as part of the south branch of the Kishwaukee River/Akins Creek), the potential for future commercial frontage, and whether the projects could be extended beyond 30 years. Petitioners said they had voluntarily reduced project footprints (one site was cut by roughly 70% during redesign) and incorporated extended landscape buffering along frontage roads to preserve opportunities for future development. They also said decommissioning and tile-repair obligations are standard parts of their agreements.
Roll-call votes approved both petitions. For the Rutland East petition (TMP25-485) the board recorded a majority of "yes" votes and two "no" votes; for Rutland West (TMP25-4655) the board likewise approved the special use with two members recorded as opposed. The zoning board of appeals and the county development committee had each recommended approval with stipulations prior to the full-board votes.
The decisions leave the villages and residents who objected without a change to the county vote; petitioners and county staff said the approvals include conditions intended to address drainage, screening and future roadway alignment. The projects’ special-use status and the 30-year operational timeframe were repeatedly cited by both opponents and supporters as central to the dispute.
Kane County staff will publish the final permit conditions and any AIMA/agency agreements associated with the projects; the petitioners indicated they will proceed with required surveys and utility coordination if the permits are recorded.